Organization Chart for Park West Project
Manpower Schedule
Manpower Deployment
Each Floor : 10 - 12 Days Target
Tile Masons - Flooring & Dado
14 Masons + 12 Helpers
Painting
8 – 10 Nos
Housekeeping & Protection
Additional 2 Men As And When Required
Grouting
4 Nos
Total Manpower Per Floor
28 Mason + 14 Helpers